Construction Sites · 4 November 2026

Uni Mail: Operation Substrate!

The substrate is being carried onto the roof of the Faculty of Psychology by a vacuum lorry.

At Uni Mail (Geneva), the material is being fed onto the roof of the Faculty of Psychology. The vacuum lorry sucks it up through hoses about 40 metres long. They rise 22 metres, then extend a further 20 metres or so.

On the roof, it is spread out in a 12-centimetre-thick layer. It takes a whole day and two trips to lay it all out. In total, 25 to 30 m³ of substrate, freshly mixed for Uni Mail.

In brief

  • 40 m hoses, from the vacuum lorry
  • 22 m elevation gain to the roof
  • 12 cm substrate on the roof
  • 25 to 30 m³ in two legs