Work in progress · Geneva (GE)

Uni Mail, Geneva: a green roof with solar panels

Underlay, solar panels, then 12 cm of substrate on the roof of the Faculty of Psychology.

9

floors, via the scaffolding

22 m

elevation gain to the roof

12 cm

substrate

25 to 30 m³

blown substrate

The project


On the roof of the Faculty of Psychology at Uni Mail, solar panels and green roofing are being installed side by side. A construction project nine storeys high, followed here step by step.

We are delighted to be able to offer this service to the Canton of Geneva, which has placed its trust in us.

Project details

VenueUni Mail, Faculty of Psychology, Geneva
Forthe canton of Geneva
Roofinglandscaped, with solar panels
Substrateproduced by Toit Vert on behalf of ZinCo, freshly brewed for Uni Mail
UnderlaysZinCo
Thanks toSedelec, and the Schöni lorry for delivery
StatusIn progress: 5 steps published

The system used and our reference points:

Image taken from Florian Chitra’s video: Uni Mail: 9 storeys up the scaffolding, and finally the roof!

9 storeys up the scaffolding, and finally the roof!

The building project, step by step


Construction work on the roof of the Faculty of Psychology at Uni Mail, with Geneva in the background

Step 1 · published on 9 October 2026

The on-site meeting on the roof

9 storeys using scaffolding, followed by coordination with the various trades to approve the technical solutions.

Read the news

Rolls of ZinCo underlay delivered on pallets to the Uni Mail premises in Geneva

Step 2 · published on 23 October 2026

The equipment is delivered

The ZinCo underlays and the panel supports are carried up to the roof via a ladder.

Read the news

Underlayment installed and supports aligned along the façade, on the roof of Uni Mail in Geneva

Step 3 · published on 26 October 2026

The underlay has been laid

Weighted supports and grating that retain some of the water.

Read the news

Solar panel mounts and a gravel buffer strip on the roof of Uni Mail in Geneva

Step 4 · published on 30 October 2026

Things are going well

Solar panel mounts installed, sterile gravel bed, aluminium gravel retainer.

Read the news

Two workers are spreading the substrate, which is being blown out through a hose, onto the roof of Uni Mail in Geneva

Step 5 · published on 4 November 2026

Substrate operation

The insulation is blown into the roof in a 12 cm layer. In total, 25 to 30 m³.

Read the news